All air-conditioning systems with a rated output of more than 12kw must be regularly inspected by an Energy Assessor. The inspections must be a maximum of five years apart. Current regulations require the first inspection of the affected air-conditioning systems to be carried out as follows:

 
 
  • For all systems first put into service on or after 1 January 2008, the first inspection must take place within 5 years of the date when it was first put into service.
  • For air-conditioning systems where the effective rated output is more than 250kw the first inspection must have taken place by 4 January 2009.
  • For air-conditioning systems where the effective rated output is more than 12kw the first inspection must have taken place by 4 January 2011.
 
 

From 4 January 2011 if the person in control of the air-conditioning system changes and the new person is not in receipt of an inspection report the new person in control must ensure the air-conditioning system is inspected within three months from the day that they assumed control.

 
 